SAFF ERP Construction
SAFF ERP Construction
Qurilish kompaniyalari uchun yagona ERP platforma.
17Modul
180Ekran
31.12.26Go-Live
Faol loyihalar24
Umumiy budjet3.42 mlrd
Bajarilish68%
Ombor12,458
Xavflar4
Modullar bo‘yicha tezkor kirish
Mobile App / AI / Telegram
Mobile App
Dashboard24 Projects86 TasksOffline ✓
ModulesProjectsWarehouseFinance
TaskChecklist 3/5PhotoDone
AI / Telegram
AI: BOQ qoldig‘i qancha?
162.5 mln UZS · source cited
Telegram: KPI today · read-only
VOBEX SYSTEMS · SAFF ERP CONSTRUCTION · BASELINE v1.0
To‘liq loyiha rejasi
Word hujjatdagi ishchi boshqaruv rejasining saytga moslashtirilgan ko‘rinishi.
ProductSAFF ERP Construction
Project ManagerOtabek Vaxobov
Deadline31.12.2026
TillarUZ / RU / EN
1. Project baseline va boshqaruv qoidalari
Deadline sharti: 19,5 haftalik tezlashtirilgan reja dedicated 9–11 kishilik jamoa bilan bajariladi.
| Ko‘rsatkich | Baseline |
|---|---|
| Platforma | OpenConstructionERP bazasi; React/TypeScript, FastAPI/Python, PostgreSQL |
| Release | Sprint 0 + 9 ta ikki haftalik sprint + cutover |
| Demo | Har 2 haftada working software |
| Acceptance | Internal QA → key-user training → UAT → Business Owner sign-off |
| Security | RBAC + scoped access + audit trail |
| Migration | Uysot dry-run → reconciliation → final ETL → Go-Live |
Ishni boshqarish oqimi
- Business Owner va real jarayonni aniqlash.
- Data Request Register bo‘yicha sample, blank, report va master data olish.
- BA: AS-IS/TO-BE, user story, acceptance criteria.
- UI/UX critical flow va tillarni tasdiqlash.
- Tech Lead DB/API/security review.
- Developer + QA evidence.
- Key-user training/UAT va Owner acceptance.
2. Jamoa tarkibi va etaplar
| Rol | Soni | Asosiy vazifa |
|---|---|---|
| Project Manager | 1 | Plan, sprint, risk, stakeholder, acceptance, cutover |
| Product/Business Analyst | 1–2 | Jarayon, data, user story, acceptance, UAT |
| Backend Developer | 3 | FastAPI, domain logic, DB, integrations, migration |
| Frontend Developer | 2 | React/TypeScript, multilingual UI, RBAC screens |
| UI/UX Designer | 1 | Design System, flows, prototype, usability |
| QA Engineer | 1→2 | Test plan, automation, regression, UAT |
| DevOps/SRE | 1 | CI/CD, env, monitoring, backup, Go-Live |
| Data/Migration | 1 | Uysot profiling, ETL, reconciliation |
Etaplar
3. Dasturchilardan talab qilinadigan natijalar
- Har task uchun estimate, dependency, acceptance criteria va technical notes.
- Kod faqat pull request orqali; kamida bitta reviewer approval.
- Unit/API/UI test; critical domainlarda negative permission testlari.
- DB migration reversible va sample data bilan tekshirilgan.
- UZ/RU/EN barcha matnlar translation key orqali; hard-coded UI text yo‘q.
- Backend role, scope, ownership va statusni tekshiradi.
- Audit log: user, action, record, old/new value, timestamp, result.
- API contract, runbook, release note va rollback ko‘rsatmasi yangilanadi.
- Sprint demo’da faqat QA’dan o‘tgan working software.
4. Har bir modul bo‘yicha xodimlardan olinadigan ma’lumot
| Modul | Ma’lumot egasi | Talab qilinadigan ma’lumot | Qabul mezoni |
|---|---|---|---|
| Executive Dashboard | CEO/CFO/COO | Oxirgi 3 oy KPI, formula/target, alert threshold | 10 KPI data source va formula bilan |
| Project 360 | Construction Director / PMO | Project register, WBS, stage/gate, team, milestone, issue/change | 1 pilot loyiha full lifecycle |
| BOQ / Smeta | Chief Estimator | BOQ Excel, resource/price catalog, unit/conversion, approval | 1 real smeta + 3 version + baseline |
| Schedule / Cost / Risk | Planner / Cost Controller | MPP/XER/Excel, calendars, baseline, progress rule, risk matrix | Pilot schedule + weekly update |
| Procurement | Procurement Head | PR/RFQ/quote/comparison/PO, vendor list, approval limits | Material va service E2E |
| Warehouse | Warehouse Head | Warehouse/bin/item, opening stock, receipt/issue/transfer/count | Opening balance + clean master |
| On Site / HSE / Quality | Site Manager / HSE | Daily report, incident, inspection, NCR, punch, permit, evidence | 1 site + 5 real case |
| Property CRM | Sales Director / Uysot Owner | Lead/customer/unit/reservation/SPA/payment/handover | 100+ sample rows + relations |
| Finance | Finance Director | Cash/bank, balances, payment requests, budget, cashflow | 1 oylik reconciliation |
| Accounting | Chief Accountant | COA, trial balance, journal, AR/AP, tax, close/report | 20 standard transaction mapping |
| HR | HR Director | Org chart, employees, contracts, shifts, attendance, leave | Active staff master + privacy |
| SMS/Marketing | CRM/Marketing/IT | Provider/API, templates, consent, triggers, campaigns | Sandbox + priority templates |
| Documents / Contracts | Legal / Office | Types, templates, numbering, approval, signatories, expiry | 20 doc types + 5 contracts |
5. Ma’lumot talabi, deadline va eskalatsiya
Har so‘rovda modul, aniq fayl/hujjat, davr, format, owner, maxfiylik, sample soni, deadline va qabul mezoni yoziladi.
| Maydon | Namuna |
|---|---|
| Request ID | FIN-DR-001 |
| Modul | Finance / Payment Request |
| Nima kerak | Oxirgi 1 oylik payment request reyestri + 5 to‘ldirilgan blank |
| Format | Excel/CSV + PDF sample |
| Davr/sample | 01.07–31.07.2026; kamida 100 qator |
| Qabul mezoni | Mandatory field ≥98%; total balans bilan mos |
- P0 data Sprint 0–1 ichida.
- P1 process/forms/reportlar developmentdan kamida 10 ish kuni oldin.
- 24 soatda receipt confirmation; 48 soatda delivery date.
- Kechikish sariq/qizil risk sifatida eskalatsiya qilinadi.
6. TXT Group ishtiroki va RACI
| Rol | Vaqt | Vazifa |
|---|---|---|
| Project Sponsor | Haftasiga 30 daqiqa | Critical decision, scope/budget/go-no-go |
| Product Owner | Kuniga 1–2 soat | Priority, acceptance, blocker resolution |
| Business Owner | Haftasiga 2×90 daqiqa | Jarayon, data, approval, UAT |
| Key User | Sprintda 4–6 soat | Prototype review, test data, training/UAT |
| IT/Security | Haftasiga 2–4 soat | Access, infra, security, integration |
RACI: R = bajaradi; A = yakuniy javobgar/tasdiqlaydi; C = maslahat/ishtirok; I = xabardor.
7. Sprint va milestone rejasi
| Sprint | Sana | Scope | Gate |
|---|---|---|---|
| S0 | 17–21 Aug | Kickoff, RACI, data request, discovery | Charter + P0 request |
| S1 | 24 Aug–4 Sep | Audit, architecture, DB/i18n/RBAC | Gap matrix approval |
| S2 | 7–18 Sep | Foundation, Design System, environments | Foundation demo |
| S3 | 21 Sep–2 Oct | Project 360, BOQ, Schedule/Cost/Risk | Construction demo |
| S4 | 5–16 Oct | Procurement, On Site, Property CRM | Operations/sales UAT |
| S5 | 19–30 Oct | Finance | Finance acceptance |
| S6 | 2–13 Nov | Accounting + posting | Accounting acceptance |
| S7 | 16–27 Nov | Warehouse + HR | Warehouse/HR acceptance |
| S8 | 30 Nov–11 Dec | SMS, Marketing, Documents, integrations | Release Candidate |
| S9 | 14–25 Dec | Regression, UAT, security, training, Uysot dry-run | Go/No-Go |
| Cutover | 26–31 Dec | Freeze, final migration, Go-Live | Production acceptance |
8. Definition of Ready / Done
Ready
- Business Owner, user role va business value aniqlangan.
- AS-IS/TO-BE, fields, statuses va approval route tasdiqlangan.
- Real sample data va data dictionary mavjud.
- UZ/RU/EN labels va permission acceptance mavjud.
- UX flow/prototype, API/DB dependency va test scenario review qilingan.
Done
- Code review, CI checks, migration va unit/API/UI/RBAC testlari pass.
- UZ/RU/EN va fallback tekshirilgan.
- Audit log, monitoring, error handling ishlaydi.
- Documentation/release note/runbook yangilangan.
- Demo, training, UAT evidence va Business Owner acceptance mavjud.
- P1/P2 defect yo‘q.
9. Birinchi 10 ish kuni va PM checklist
- Kickoff; Sponsor/PO/Business Ownerlarni tasdiqlash.
- P0 Data Request Register yuborish.
- Repository, Uysot sample, infra va API access.
- OCE code/DB/security/license audit.
- Project/BOQ/Schedule/Procurement workshops.
- Sales/Uysot va Finance/Accounting workshops.
- Warehouse/HR/Marketing/Admin workshops.
- Master Data Dictionary + RBAC matrix.
- 3-language critical flows prototype.
- Audit readout va baseline confirmation.
PM kundalik checklist
- Har taskda owner, deadline, acceptance va dependency bormi?
- Business Owner va key-user calendar’da bormi?
- Overdue Data Request bormi?
- PR/code review/test evidence mavjudmi?
- UZ/RU/EN va RBAC scope test qilindimi?
- P1/P2, security yoki migration blocker bormi?
- Sponsor/POdan 24 soatda olinadigan qaror bormi?
Source: SAFF_ERP_Construction_Complete_Project_Plan_itogoviy.docx · Baseline v1.0 · 15.08.2026